Which cross drainage work is constructed to carry canal over drainage?
A
Aqueduct
B
Super passage
C
Canal syphon
D
Level crossing
Q2448
Permalink
Report
Which cross drainage work is constructed to carry canal below drainage?
A
Aqueduct
B
Super passage
C
Level crossing
D
Inlet
Q2449
Permalink
Report
Which cross drainage work is constructed to cross the canal and drainage at the same level?
A
Aqueduct
B
Super passage
C
Canal syphon
D
Level crossing
‹
1
2
›
Report Question Issue
Your Name (Optional)
Your Email (Optional)
What do you think is the correct answer?
*
-- Select the correct answer --
A
B
C
D
Select which option you believe is the correct answer.
Feedback
*
Verify you're human
*
Loading...